Enterprise Research Campus Update #120 (Week of December 15, 2025)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Streetscape & Western Ave

Weekend Activities

  • No work will take place this weekend.

Weekday/night Activities

  • Sidewalk ramp installation, manhole/drain work and electrical conduit install across and on the Harvard Business School side of Western Avenue will continue. The roadway will be narrowed and two-way traffic maintained with police, cones and signage to direct traffic. The work will begin at 9:30 a.m. and the trenches will be backfilled and/or plated at the end of each shift.
  • Conduit work for light poles will take place at the entrance of Kresge Way. One half of the roadway will be closed at a time, always maintaining access to the Soldiers Field Garage and Harvard Business School. Police details will be directing traffic, cyclists and pedestrians around the traffic.
  • Due to cold weather conditions, the resurfacing of Western Avenue will take place during warmer weather, most likely in the spring.
  • The fence between Hague Street and Trotting Avenue will be moved off the street at the end of the week.
  • Paver and asphalt install will take place.
  • Site furnishes will be installed.
  • General clean-up and fence removal will take place.

Building Mock-Ups

  • Removal of the building mockups on the corner of Hague and Rotterdam Streets is finishing up. underway. Site clean up and grading will be underway. A lane on Rotterdam Street will be used intermittently. Mock-up materials will be disposed of inside the site with equipment using the Hague Street gate.

Residential Hotel

Weekend Activities

  • On Saturday, December 13, crews will be splitting up the triple-wide trailer off Trotting Avenue and painting in the hotel will be underway.
  • On Sunday, December 14, no work will take place.

Weekday/Night Activities

  • The triple-wide trailer sections at Trotting Avenue will be removed from site exiting via Milestone Street.
  • Move-ins continue at the midrise and highrise residential buildings (Verra).
  • Generators and heaters will be used while crews waterproof underground tanks for recaptured water.
  • The hotel has its temporary certificate of occupancy.
  • Punch list work continues in the midrise, highrise, hotel and podium.
  • Some elevator work continues in the hotel and garage.
  • Garage clean-up and finish work is underway.
  • Furniture and other operator supplies continue to be delivered to the hotel.

Laboratory and Office Buildings

Weekend Activities

  • On Saturday, December 13,  penthouse mechanical, elevator, interior lobby and miscellaneous general clean-up work will be underway.
  • On Sunday, December 14, four electrician programmers and ten elevator installers will be working.

Weekday Activities

  • Preparation and clean-up for testing and inspections will be ongoing. Boston Fire Department tests including fire-alarm testing may be scheduled off hours and may generate some noise.
  • Elevators are being adjusted and inspected.
  • MEP detail and start up activities are ongoing.
  • Mechanical penthouse detail and start up activities continue.
  • Lobby and other fit out detail work continues.
  • Garage finish work continues.
  • Punch-list work is underway on the building’s interior and exterior as well as on the land/hardscaping areas.

Treehouse Conference Center

Weekend Activities in Coordination with Treehouse Operations

  • No weekend construction work will take place.

Weekday Activities in Coordination with Treehouse Operations

  • Interior and operational punch list activity will continue.
  • Operational deliveries and work will take place.
  • Exterior punch list activity will begin on Wednesday, December 17.

Greenway

Weekend Activities

  • On Saturday, December 13, possible landscaping and deck work may take place.
  • On Sunday, December 14, no work will take place.

Weekday Activities

  • Pavers will continue to be placed near the water features, at the shared use path and other areas.
  • Bioswale boardwalk detail work is underway.
  • Hardscape furnishings are being installed.
  • Punchlist work continues.

General

  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m. Crews will coordinate work in accordance with building operations for those buildings that have opened.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Weekly flights are weather dependent and are scheduled one weekday morning.
    • A drone flight is planned on Thursday, December 18.