All project sites will be closed on Friday, July 4.

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

Weekend Activities

  • On Saturday, July 5, exterior louvers and lighting will be installed at the high-rise residential building with several boom lifts operating. Elevator and miscellaneous interior work is ongoing in all three buildings.
  • On Sunday, July 6, twelve workers will be inside the midrise and high-rise building elevator shafts. Eight workers will be onsite to conduct cleaning operations in the mid-rise building. Six workers will be in the mid-rise installing tile.

Weekday/Night Activities

  • Preparation is underway for a temporary certificate of occupancy this week in the midrise residential building
  • Fire standpipe testing will take place on Tuesday 5 a.m. and will result in water flowing into nearby drains at Western Avenue and inside the site.
  • Crews are scheduled to work in the evenings at the high-rise, exterior façade from 3 to 11 p.m. on swing staging with portable light towers pointed at the building.
  • Exterior curtainwall installation will take place on the highrise with temporary lighting into the evening activity from 3 to 11 p.m.
  • Paver activities and possible interior highrise work will occur from 11 p.m. – 7 a.m.
  • Exterior wall sheathing, panel clips and green exterior panels are being installed on the highrise building.
  • At the high rise, the hoist has been removed and infill work is underway.
  • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the hotel.
  • Mast climber scaffolding and swing staging are set up on the high-rise building.
  • Elevator installation activity continues.
  • Smaller concrete operations continue.
  • MEP work is ongoing.
  • Framing, drywall and bathroom installation are taking place inside the buildings.
  • Flooring and painting are underway.

Laboratory and Office Buildings

Weekend Activities

  • No work is planned this weekend.

Weekday Activities

  • A crane will be on site to install infill curtainwall where the hoist was located.
  • The loading dock demolition is finishing.
  • Boom lifts are active around the perimeter of the buildings.
  • Level 1 soffit and exterior work is underway.
  • Smaller concrete operations continue.
  • Roof activities are underway.
  • Elevators are being installed and inspected.
  • MEP work is ongoing.
  • Mechanical penthouse activities continue.
  • Masonry work continues.
  • Structural soil backfill, low voltage, concrete pad and granite curb install will take place on the east side of the buildings.
  • Framing, drywall and bathroom install are underway.

Treehouse Conference Center

Weekend Activities

  • Work includes flooring, drywall, elevator and miscellaneous interior work including MEP activity on Saturday, July 5.
  • On Sunday, July 6, twelve roofers will be working.

Weekday/Night Activities

  • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
  • Wood trim panels and other façade installation continue.
  • Duct bank excavation and install is occurring.
  • Framing and drywall continue.
  • Elevator work is underway.
  • MEP activities are ongoing.
  • Flooring work continues.
  • Small concrete placements will take place.
  • Bathroom work continues.
  • Painting is underway.
  • Connection work will occur.

Evening Thermal Work

  • Underground backfilling work and final connection work to the Treehouse may take place from 4 p.m. until midnight.

Greenway

Weekday Activities

  • Landscaping crews continue prepping for hardscape.
  • Light pole bases are being installed.
  • Prep and utility work is underway for water features.
  • Outcropping (boulder) install continues.

Streetscape

Weekday/Night Activities

  • Daytime work includes sidewalks, curbing, paver install near the buildings. Piping will begin to be installed along Milestone St.
  • Evening crews will be prepping for the bike lane, curbing, railings, trash receptacles from 3 p.m. to 10 p.m. All work will be contained within the site.

Building Mock-Ups

  • Building mockups are on the corner of Hague and Rotterdam Streets.
  • A pedestrian pathway from the Hague Street lot to the street is being completed.

Eversource Conduit Project

  • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.

General

  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Weekly flights are weather dependent and are scheduled one weekday morning.
    • A drone is scheduled to fly on Thursday, July 10, at 3 p.m.