As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
Holiday Weekend Activities
- On Saturday, April 19, exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the infill hoist area. Elevator and miscellaneous interior work with operational hoists at all three buildings are planned.
- On Patriot’s Day, Monday, April 21, carpenters and plumbers will be working inside the mid-rise and high-rise buildings. Hoists will be operational.
Weekday Activities
- Eversource may be on site making connections between their Trotting Avenue manhole and the building.
- Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
- At the midrise the hoist has been removed and infill work is underway.
- Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
- hotel.
- Mast climber scaffolding and swing staging are set up on the high-rise building.
- Elevators are being installed.
- Other concrete operations continue.
- Roofing activities are underway.
- MEP work is ongoing.
- Framing and bathroom installation are taking place inside the buildings.
- Temporary heaters are being removed.
Laboratory and Office Buildings
No construction work will be taking place this holiday weekend.
Weekday Activities
- Boom lifts are active around the perimeter of the buildings.
- Level 1 soffit and exterior work is underway.
- Smaller concrete operations continue.
- Roof activities are underway.
- Elevators are being installed.
- MEP work is ongoing.
- Mechanical penthouse activities continue.
- Masonry work continues.
- Framing and bathroom install are underway
- Spray-on insulation work will take place.
- Temporary heaters are being disconnected.
Greenway
- Landscaping crews continue prepping for hardscape and tree planting.
- Trees will begin to be planted.
Treehouse Conference Center
Holiday Weekend Activities
- Work includes façade, sub-floor, insulation and dry-wall installation as well as roofing activity on Saturday, April 19. A duct bank delivery will take place.
- No construction work will be taking place on Patriot’s Day, Monday, April 21.
Weekday Activities
- Façade frame and glass installation continues during the week using boom lifts.
- Roofing and terrace activities are underway.
- Framing and drywall continues.
- Elevator work has begun.
- MEP activities are ongoing.
- Sub-flooring work continues
- Small concrete placements will take place.
Streetscape
- Duct bank and road work excavation has begun.
Western Ave. Roadway Work
- Nighttime utility tie-in work is scheduled to take place in front of the Treehouse Conference Center site on Western Avenue, Tuesday, April 22 through Friday, April 25 from 7 p.m. to 5 a.m.
- Between Hague and Milestone streets, pedestrians will shift at night to the Harvard Business School side of the road and cyclists will share the road during these activities.
- A vehicular travel lane will be taken when crews are working in sewer manholes.
- Signage will be in place and two police details will be scheduled. Two-way traffic will be maintained.
- Crews will also be patching the roadway at night.
- The roadway will be plated during the day and on the weekend.
Building Mock-Ups
- Building mockups are on the corner of Hague and Rotterdam Streets.
Eversource Conduit Project
- Eversource duct bank installation by G. Greene Construction is underway along Western Avenue. Crews are near Travis Street. This public utility work is not under the supervision of ERC.
General
- The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
- Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
- Drones will be in use bi-weekly to monitor construction progress on site.
- Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
- Weekly flights are weather dependent and are scheduled one weekday morning.
- A drone is scheduled to fly Thursday, April 24 at 2:30 p.m.