Enterprise Research Campus Update #76 (Week of February 3, 2025)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • On Saturday, February 1, panel installation will take place on the residential buildings with several boom lifts operating. Roofing activities will be underway on the high rise and hotel. Elevator and other miscellaneous interior work with hoists operational are planned.
  • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
  • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
  • Storefront installation is underway on the ground floors.
  • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
  • Elevators are being installed.
  • Other smaller concrete operations continue.
  • Roofing activities are underway.
  • MEP work is ongoing.
  • Framing and bathroom install are taking place inside the buildings.
  • Temporary heaters are operating.

Laboratory and Office Buildings

  • On Saturday, February 1, roofing materials will be delivered and unloaded using the tower crane. Curtain wall will be installed. Boom lifts will be used to install exterior Interior drywall framing and mechanical work will be underway. 
  • Installation of exterior curtain-wall panels will take place during the week.
  • Boom lifts are active around the perimeter of the buildings.
  • Level 1 exterior work is underway.
  • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
  • Smaller concrete operations continue.
  • Roof activities are underway.
  • Elevators are being installed.
  • MEP work is ongoing.
  • Mechanical penthouse activities continue.
  • Masonry work continues.
  • Framing and bathroom install are underway
  • Temporary heaters are operational.

Greenway

  • Backfilling continues with the site leveling off
  • Some drainage work is underway.

Treehouse Conference Center

  • Mass timber and façade activities will take place on Saturday, February 1. A crane will be in operation.
  • Mass timber activities and installation are finishing up.
  • Façade frame installation continues during the week using boom lifts.
  • Possible concrete core placements if weather permits.
  • MEP activities are ongoing.

Building Mock-Ups

  • Building mockups are on the corner of Hague and Rotterdam Streets.

Eversource Conduit Project

  • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. This public utility work is not under the supervision of ERC.

General

  • Snow and ice removal and cleanup will take place as needed.
  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
  • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Weekly flights are weather dependent and are scheduled one weekday morning.
    • A drone is scheduled to fly Thursday, February 6 from 7 a.m. to 9 a.m.