As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- On Saturday, December 7, boom lifts will be set up on Trotting Avenue with exterior wall and roofing activity underway. Miscellaneous interior work with hoists operational is planned.
- Windows, exterior sheathing, framing and waterproofing are also being installed during the week on the residential buildings.
- Exterior panel installation is ongoing at the hotel.
- A suspended scaffolding deck like under a bridge is set up on the underside of the cantilever section at the hotel.
- Mast climber scaffolding will be installed on the high-rise building.
- Elevators are being installed.
- Other smaller concrete operations continue.
- Roofing activities are underway.
- MEP work is ongoing.
- Framing is taking place in certain areas of the building.
- Temporary heaters are being set up.
Laboratory and Office Buildings
- On Saturday, December 7, piping deliveries will occur with the tower crane operational. Eversource and their equipment will be at ground level. Exterior façade work and general cleanup will also be underway.
- State police-escorted oversize trucks will deliver air handlers on Monday, December 9, Tuesday, December 10, Wednesday, December 11 and Thursday, December 12 at 5 a.m. The tower crane will be used to unload the trucks after 7 a.m.
- The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
- Exterior curtain-wall panels are being installed during the week.
- Smaller concrete operations continue.
- Roof activities are underway.
- MEP work is ongoing.
- Mechanical penthouse activities continue.
- Masonry work continues.
- Temporary heaters are being set up.
Greenway
- Drainage structures and pipe installation are underway.
- Concrete activity for the rainwater storage tank will continue.
- Backfilling continues.
Treehouse Conference Center
- Removal of scaffolding will take place on Saturday, December 7. A crane will be in operation.
- Mass timber deliveries, activities and installation of the mezzanine decks and roof beams will be underway with a crane operating during the week.
- MEP activities and miscellaneous utilities are ongoing.
Waterline Installation on Western Ave.
- Relocation of the fence line back closer to Western Avenue has begun with line striping to follow on either Friday or Tuesday nights, November 29 or December 3.
Building Mock-Ups
- Building mockups are on the corner of Hague and Rotterdam Streets.
Eversource Conduit Project
- Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. This public utility work is not under the supervision of ERC.
General
- The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
- Saturday work is scheduled to take place starting at 7 a.m.
- Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
- Drones will be in use bi-weekly to monitor construction progress on site.
- Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
- Weekly flights are weather dependent and are scheduled one weekday morning.
- Drones will be flying at 8 a.m. on Friday, December 6 and Tuesday, December 10 from 8 a.m. to noon.