As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- On Saturday, September 7, crews at the high-rise residential building will continue to extend the hoist (the exterior elevator) and will work on hotel hoist. At the mid-rise windows will be installed.
- Concrete decking is finishing up.
- Other smaller concrete operations continue.
- The high-rise building has topped off at level 18.
- The mid-rise residential building has topped off at their mechanical penthouse at level 9.
- The hotel hoist and loading dock installation are finishing along Trotting Avenue.
- Windows, exterior sheathing, framing and waterproofing are being installed on the residential buildings.
- Exterior curtain-wall panels are being installed at the hotel.
- MEP work is ongoing.
Laboratory and Office Buildings
- Crews will be cleaning up, prepping for concrete placements and spraying fireproofing on Saturday, September 7.
- Exterior curtain-wall panels are being installed on the west building.
- Concrete operations continue with deck placements.
- The hoist and loading dock are finishing on the southern side of the building.
- Both east and west buildings structural steel have topped off.
- Steel decking and detailing continue on the east building.
- Roofing activities are underway.
- MEP work is ongoing.
Greenway
- Bulk excavation will take place with intermodals delivering material for rail transport to the Beacon Yard through the haul road, all inside the site.
- Backfilling, involving trucks of clean soil entering the site, is underway.
Treehouse Conference Center
- Carpenters will be installing tension straps on Saturday, September 7.
- Mass timber installation and protection work continues.
- MEP activities continue in the basement and on level one.
- Preparation for façade installation is underway
Waterline Installation on Western Ave.
- The ERC team is working with the City, Boston Water and Sewer and Harvard to replace a 12-inch waterline with a larger 16-inch waterline from Hague to Milestone streets on Western Avenue.
- The waterline replacement will take place Monday through Thursday nights from 7 p.m. to 5 a.m. and begin on Monday night, September 9.
- During the nighttime work, pedestrians will shift to the Harvard Business School side of the road and cyclists will share the road.
Building Mock-Ups
- Punchlist work and other adjustments are intermittent on all five mockups.
Eversource Conduit Project
- Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. This public utility work is not under the supervision of ERC.
Milestone Thermals
- Work will progress next week with backfilling at the southern end of Milestone Street to within the Greenway site for duct bank installation.
General
- The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
- The projects’ work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
- Saturday work is scheduled to take place starting at 7 a.m.
- Intermittent use of power trowels for concrete finishing and layout for concrete placement may take place after 6 p.m.
- Drones will be in use bi-weekly to monitor construction progress on site.
- Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
- Flights are weather dependent and are scheduled one weekday morning alternating weekly.
- A drone progress flight is not scheduled for next week.