As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Saturday, August 10 outside wall operations will take place as well as formwork on Level 18 of the high-rise with use of the crane. This work is weather dependent.
- Concrete decking and other operations continue.
- Hotel steel installation has topped off at level 17 and continues with work on the periscope, the cantilevered section of the building.
- The mid-rise residential building has topped off at their mechanical penthouse at level 9.
- The hoists (exterior construction elevators) and loading docks have been installed. The mid-rise hoist is operational.
- Work is progressing to level 18 of the high-rise building.
- Exterior sheathing is being installed on the residential buildings.
- Exterior curtain-wall panels are being installed at the hotel.
- MEP work is ongoing.
Laboratory and Office Buildings
- The tower crane jump, meaning to be built up to a new height, occurred this week.
- Workers will be on site for steel activities and for concrete preparation in the parking garage.
- Concrete operations continue with deck placements.
- The hoist is being installed on the southern side of the building.
- Structural steel continues to be delivered and installed on the east building with decking and detailing on the west building.
- The east building steel is up to level 8, and the west building has topped off finishing structural steel on the second mechanical penthouse above level 9.
- Utility installation is underway on the perimeter of the site.
- MEP work is ongoing.
Greenway
- Erection of the fence line and excavation of the fence line area is underway.
Treehouse Conference Center
- A crew will be installing mass timber this Saturday, August 10 starting at 7 a.m. A crane and lifts will be in use.
- Mass timber installation and protection work continues next week.
- Core connection work continues.
- Thermal activities for East Drive (Milestone Street) is underway.
Building Mock-Ups
- Punchlist work and other adjustments are intermittent on all five mockups.
General
- The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
- The projects’ work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
- Intermittent use of power trowels for concrete finishing and layout for concrete placement may take place after 6 p.m.
- Drones will be in use bi-weekly to monitor construction progress on site.
- Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
- Flights are weather dependent and are scheduled one weekday morning alternating weekly.