Enterprise Research Campus Update #40 (Week of May 13, 2024)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Work will be underway this Saturday, May 13, starting at 7 a.m.
    • Crews will be preparing for concrete placements and steel detailing.
    • Tower cranes will be operational.
  • Structural steel continues to be delivered and installed at the hotel, rising up to Level 10.
  • Concrete operations are ongoing.
  • Utility tie-ins continue inside the site on Trotting Avenue.
  • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.
  • Visible work is underway with work progressing to level eight and nine of the high rise and midrise residential buildings.

Laboratory and Office Buildings

  • Work will be underway this Saturday, May 13, starting at 7 a.m.
    • Crews will be erecting steel.
  • The two tower cranes are operating and structural steel continues to be delivered and installed on both the east and west buildings.
  • Concrete placements will take place on the first floor and on the ramp.

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • Work will take place this Saturday, May 13, starting at 7 a.m.
    • Crews will be preparing for placements.
    • Masons will be working on the core.
    • Two cranes are operating on site.
  • Work is underway on the elevator cores with a concrete wall placement next week.
  • Crews are preparing for mass timber install later this month.
  • Final inspections and connections for temporary power are expected. Eversource may intermittently be on site and off Western Avenue.

Building Mock-Ups

  • Punchlist work and other adjustments are ongoing on all five mockups.

General

  • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating weekly.
    • The drone flight is planned for Thursday, May 16 at 7 a.m.