As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Work will be underway this Saturday, March 23 starting at 7 a.m.
- Crews will be preparing for concrete placements.
- Core equipment removal will be taking place.
- Tower cranes will be operational.
- Concrete operations are ongoing.
- Intermittent use of power trowels for concrete finishing may take place after 6 a.m.
- The hotel core is complete.
- Visible work is underway on level three of the high rise and midrise residential buildings.
Laboratory and Office Buildings
- Structural steel continues to be delivered and installed and rising to the second level on the of the west tower using the tower crane.
- Drainage stone will be placed on the east building.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- Work will take place this Saturday, March 23, starting at 7 a.m.
- Concrete crews will be preparing for placements.
- Work is underway on the elevator core.
- Backfilling is underway.
- Concrete placements are ongoing.
- Temporary power is being installed on site. Eversource may use a vacuum truck.
Building Mock-Ups
- Punchlist work is ongoing on all five mockups.
General
- The site’s three tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
- Drones will be in use bi-weekly to monitor construction progress on site.
- Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
- Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7 a.m. to 9 a.m. alternating weekly.
- A drone flight is scheduled for Friday, March 22 from 10 a.m. to noon.
- After hours snow removal operations will be ongoing during periods of inclement weather.