Enterprise Research Campus Update #28 (Week of February 19, 2024)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

All sites will not be working on the holiday, Monday, February 19th.

Residential/Hotel

  • There will be work this Saturday, February 17th, starting at 7AM.
    • Crews will be preparing for concrete placements.
    • Tower cranes will be operational.
  • Concrete operations are ongoing.
  • Intermittent use of power trowels for concrete finishing may take place after 6PM.
  • Crews continue erecting the hotel core structure.
  • Visible work is taking place on the sky deck and level two.
  • Temporary overhead power will be installed on site to power the field trailers and eliminate remaining generators on site.
  • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

Laboratory and Office Buildings

  • There will be work this Saturday, February 17th, starting at 7AM.
    • Crews will be placing crushed stone on the foundation bottom.  No trucking in or out.
  • Concrete and rebar operations are ongoing.
  • Continue to place crushed stone on the foundation bottom.
  • Crews are preparing for the first of two tower cranes to be erected on Saturday, February 24th and Sunday, February 25th.
    •  A 6AM start and possible after-hours work will be needed to support this operation.
  • Temporary power is being installed on site

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • There will be work this Saturday, February 17th, starting at 7AM.
    • Concrete crews will be preparing for wall placements.
  • Concrete placements and rebar operations are ongoing.
  • Temporary power is being installed on site.

Building Mock-Ups

  • Work will take place at the Residential/Hotel mockups.
  • Treehouse Conference Center mockup is awaiting Mass Timber delivery.
  • Punchlist work is ongoing at the Laboratory mockup.
  • A lane shift around lifts and Intermittent deliveries will take place on Rotterdam Street.

General

  • Drones will be in use weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7AM to 9AM alternating weekly.
    • No drone flights are scheduled next week.
    • A drone flight will take place on Thursday, February 22nd from 7AM to 9AM.
  • After hours snow removal operations will be ongoing throughout the winter months during periods of inclement weather.