Enterprise Research Campus Update #23 (Week of January 15, 2024)

All sites will have crews working on Monday, January 15th.

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • There will be work this Saturday, January 13th starting at 7AM.
    • Preparation for concrete placements will be underway.
    • Tower cranes will be operational.
  • Concrete operations are ongoing. Intermittent use of power trowels for concrete finishing will take place after 6PM.
  • Crews continue erecting the hotel core structure.
  • More visible work is taking place on the sky deck and level two.
  • A large generator is operating to provide temporary power to the site.
    • This generator will run 24/7 to support the power needs, especially heaters, on the site until installation of temporary power is complete.
  • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

Laboratory and Office Buildings

  • There will be no work on site this Saturday.
  • Concrete and rebar operations are ongoing.
    • Crews are working on wall placements with two to three placements a week.
  • Excavation of the site’s east berm will continue.

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • There will be work this Saturday, January 13th starting at 7AM.
    • Iron workers, electricians, and plumbers will be working within the site foundation.
  • A 300-yard slab placement is scheduled for Friday, January 19th. Concrete finishers with power trowels will be on site.
  • Concrete and rebar operations are ongoing.

Building Mock-Ups

  • Sheeting work will take place at the Residential/Hotel mockups.
  • Mass Timber delivery is expected at the Treehouse Conference Center mockup.
  • Punchlist work is ongoing at the Laboratory mockup.