As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- There will be work this Saturday, December 9th starting at 7AM.
- Crews will be doing backfilling work.
- Concrete operations are ongoing.
- Multiple placements are scheduled to take place over the next two weeks.
- These placements will start during normal work hours.
- Finishing work may continue past normal operation hours.
- Multiple placements are scheduled to take place over the next two weeks.
- Waterproofing work continues on the site foundation.
- A large generator has been installed to provide temporary power to the site.
- This generator will run 24/7 to support the power needs, especially heaters, on the site.
- The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
Laboratory and Office Buildings
- Concrete and rebar operations are ongoing.
- Waterproofing work continues on the site foundation.
- There will be work this Saturday, December 16th starting at 2:30AM.
- A 4,500-yard placement will take place.
- The site lights will be turned on at 2AM.
- A 4,500-yard placement will take place.
- Formwork and raker post activities will continue.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- There will be work this Saturday, December 16th starting at 7AM.
- Crews will be preparing for formwork installation.
- Concrete operations are ongoing with a mud mat placement scheduled for Tuesday, December 19th.
- Rebar installation will begin next week in preparation for a January mat slab placement.
Building Mock-Ups
- Crews continue to work at the Laboratory and Hotel mockups.
- Work will continue at the Residential and Treehouse Conference Center mockups at the end of December.