Enterprise Research Campus Update #20 (Week of December 18, 2023)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • There will be work this Saturday, December 9th starting at 7AM.
    • Crews will be doing backfilling work.
  • Concrete operations are ongoing.
    • Multiple placements are scheduled to take place over the next two weeks.
      • These placements will start during normal work hours.
      • Finishing work may continue past normal operation hours.
  • Waterproofing work continues on the site foundation.
  • A large generator has been installed to provide temporary power to the site.
    • This generator will run 24/7 to support the power needs, especially heaters, on the site.
  • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

Laboratory and Office Buildings

  • Concrete and rebar operations are ongoing.
  • Waterproofing work continues on the site foundation.
  • There will be work this Saturday, December 16th starting at 2:30AM.
    • A 4,500-yard placement will take place.
      • The site lights will be turned on at 2AM.
  • Formwork and raker post activities will continue.

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • There will be work this Saturday, December 16th starting at 7AM.
    • Crews will be preparing for formwork installation.
  • Concrete operations are ongoing with a mud mat placement scheduled for Tuesday, December 19th.
  • Rebar installation will begin next week in preparation for a January mat slab placement.

Building Mock-Ups

  • Crews continue to work at the Laboratory and Hotel mockups.
  • Work will continue at the Residential and Treehouse Conference Center mockups at the end of December.