As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation operations have been completed.
- Concrete operations on site will continue.
- Rebar work within the site foundation is ongoing.
- There will be work this Saturday, December 9th starting at 7AM.
- Crews will be doing rebar work.
- A 2,000-yard hotel core mat placement will take place on December 14th.
- This operation will start at 5AM with the lights turned on at 4:30AM.
- Waterproofing work continues on the site foundation.
- A large generator will be installed to provide temporary power to the site.
- This generator will run 24/7 to support the power needs, especially heaters, on the site.
- The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
Laboratory and Office Buildings
- Concrete and rebar operations are ongoing.
- Waterproofing work continues on the site foundation.
- There will be work this Saturday, December 9th starting at 7AM.
- Crews will be doing carpentry work.
- An additional crane will be onsite to lower formwork into the foundation.
- The third mat slab placement is scheduled for December 16th.
- This 4,500-yard placement will start at 2:30AM.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- There will be work this Saturday, December 9th starting at 7AM.
- Crews will be preparing for formwork installation.
- Concrete operations will begin with a mud mat placement on Friday, December 8th.
Building Mock-Ups
- Crews continue to work at the Laboratory and Hotel mockups.
- Steel delivery will take place on December 12th for the Conference Center mockup.
- A crane will unload the steel from a trailer parked on Rotterdam Street between 9AM-10AM.
- Work will continue at the Residential mockup at the end of December.