As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation operations will be completed Friday, December 1st.
- Concrete operations on site will continue.
- Rebar work within the site foundation is ongoing.
- There will be work this Saturday, December 2nd starting at 7:00am.
- Crews will be working within the site foundation.
- Crews are preparing for a 2,000-yard hotel core mat placement on December 14th.
- This operation will start at 5:00am with the lights turned on at 4:30am.
- The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
Laboratory and Office Buildings
- Concrete and rebar operations are ongoing.
- Waterproofing work continues on the site foundation.
- There will be work this Saturday, December 2nd starting at 5:00am.
- Crews will be placing a 2,000 -yard second mat slab.
- The lights will be turned on at 4:30am.
- A triple wide trailer will be delivered to site on Monday, December 4th between 5am and 7am.
- The third mat slab placement is scheduled for December 16th.
- This 4,500-yard placement will start at 2:30am.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- Intermodal trucking operations have been completed.
- Stone deliveries are ongoing to be placed in the site foundation.
- There will be work this Saturday, December 2nd starting at 7:00am.
- Crews will be lining the site’s foundation with stone.
- Excavation operations will take place with no trucking.
Building Mock-Ups
- Crews will continue work on the Laboratory mockup starting Monday, December 4th.
- At the Hotel mockup steel has been erected and crews continue fabrication of the mockup.
- Work will continue at the Residential and Conference Center mockups at the end of December.