As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation and concrete operations on site will continue.
- Rebar work within the site foundation is ongoing.
- There will be work this Saturday, November 25th, and Sunday, November 26th.
- The second tower crane will be erected on site.
- A 5AM start Saturday and 7AM start Sunday is needed for this operation.
- The first of two tower cranes has been erected and is operational. It is designed to move or “weathervane” in the wind.
Laboratory and Office Buildings
- Concrete and rebar operations are ongoing.
- Waterproofing work continues on the site foundation.
- There will be no work this Saturday.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- Excavation operations on site will continue.
- Soil is being hauled by intermodals to the rail.
- A private haul road is used to transport soil onto the rail at Beacon Park Yard.
- There will be no work this Saturday.
Building Mock-Ups
- Steel deliveries and concrete operations are ongoing for the Treehouse Conference Center mockup.