As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation and concrete operations on site will continue.
- Rebar work within the site foundation is ongoing.
- There will be no work this Saturday, November 11th.
- The first of two tower cranes has been erected and is operational. It is designed to move or “weathervane” in the wind.
- A mat placement is currently planned for Monday, November 20th requiring a 5AM start.
- The second tower crane is targeted to be erected the weekend of November 25th & 26th.
- A 5:00am start is needed both days for this operation.
Laboratory and Office Buildings
- Bulk excavation of the site is nearing completion.
- Concrete operations are ongoing.
- Rebar work is ongoing in preparation for a large mat slab placement on November 18th.
- An early start of 2:30AM is needed to accommodate this large pour.
- Waterproofing work continues on the site foundation.
- There will be work this Saturday, November 11th, starting at 7AM.
- Carpentry crews will be working within the site foundation.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- Excavation operations have resumed.
- Soil is being hauled by highway trucking and intermodals to the rail simultaneously.
- A private haul road is used to transport soil onto the rail at Beacon Park Yard.
- There will be no work this Saturday, November 11th.
Building Mock-Ups
- The Residential/Hotel and Treehouse Conference Center mockup’s concrete pad work is ongoing.
- This will be followed by steel work.