Enterprise Research Campus Update #15 (Week of November 13, 2023)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Bulk excavation and concrete operations on site will continue.
    • Rebar work within the site foundation is ongoing.
  • There will be no work this Saturday, November 11th.
  • The first of two tower cranes has been erected and is operational. It is designed to move or “weathervane” in the wind.
  • A mat placement is currently planned for Monday, November 20th requiring a 5AM start.
  • The second tower crane is targeted to be erected the weekend of November 25th & 26th.
    • A 5:00am start is needed both days for this operation.

Laboratory and Office Buildings

  • Bulk excavation of the site is nearing completion.
  • Concrete operations are ongoing.
  • Rebar work is ongoing in preparation for a large mat slab placement on November 18th.
    • An early start of 2:30AM is needed to accommodate this large pour.
  • Waterproofing work continues on the site foundation.
  • There will be work this Saturday, November 11th, starting at 7AM.
    • Carpentry crews will be working within the site foundation.

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • Excavation operations have resumed.
    • Soil is being hauled by highway trucking and intermodals to the rail simultaneously.
    • A private haul road is used to transport soil onto the rail at Beacon Park Yard.
  • There will be no work this Saturday, November 11th.

Building Mock-Ups

  • The Residential/Hotel and Treehouse Conference Center mockup’s concrete pad work is ongoing.
    • This will be followed by steel work.