Enterprise Research Campus Update #9 (Week of October 2, 2023)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Bulk excavation and concrete operations on site will continue.
  • Preparation continues for installing the first of two tower cranes
    • On Tuesday a crane will be on site to set the base of the crane.
    • A 1,000-yard concrete placement is planned to take place on Thursday for the tower crane foundation.
      • A start time of 5:00am is planned to accommodate this large-scale pour.
    • The first of two tower cranes will be set up over a weekend in the coming weeks.
  • Concrete crews will be working this Saturday, September 30th, starting at 9:00am.

Laboratory and Office Buildings

  • Bulk excavation of the site continues.
  • Crews continue to line the site foundation with stone and pour mud mat.
  • Work will take place this Saturday, September 30th, starting at 9:00am.
    • Crews will be relocating the wheel wash station and stock piling soil inside the hole.

Greenway

  • This section of the site is currently being used for laydown space until crews mobilize in the coming months.

Treehouse Conference Center

  • Crews have mobilized operations as construction begins.
  • Preclearing and soil remediation operations will begin Monday, October 2nd.
    • Soil will be hauled out via rail at Beacon Park Yard.

Building Mock-Ups

  • Work is nearly complete on the first two of five visual mockups.