As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation and concrete operations on site will continue.
- Preparation continues for installing the first of two tower cranes
- On Tuesday a crane will be on site to set the base of the crane.
- A 1,000-yard concrete placement is planned to take place on Thursday for the tower crane foundation.
- A start time of 5:00am is planned to accommodate this large-scale pour.
- The first of two tower cranes will be set up over a weekend in the coming weeks.
- Concrete crews will be working this Saturday, September 30th, starting at 9:00am.
Laboratory and Office Buildings
- Bulk excavation of the site continues.
- Crews continue to line the site foundation with stone and pour mud mat.
- Work will take place this Saturday, September 30th, starting at 9:00am.
- Crews will be relocating the wheel wash station and stock piling soil inside the hole.
Greenway
- This section of the site is currently being used for laydown space until crews mobilize in the coming months.
Treehouse Conference Center
- Crews have mobilized operations as construction begins.
- Preclearing and soil remediation operations will begin Monday, October 2nd.
- Soil will be hauled out via rail at Beacon Park Yard.
Building Mock-Ups
- Work is nearly complete on the first two of five visual mockups.