As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Bulk excavation and concrete operations on site will continue.
  • Rebar work within the site foundation is ongoing.
  • Work will take place on Saturday, October 28th.
  • Crews will start at 7:00am doing excavation work.
  • All work will take place within the site.
  • Soil will be transported via intermodal trucks via the site haul road to Beacon Park Yard.
  • The first of two tower cranes has been erected and is operational. It is designed to move or “weathervane” in the wind.

Laboratory and Office Buildings

  • Bulk excavation and concrete operations on site will continue.
  • Rebar work is ongoing in preparation for the mat slab placement.
  • Waterproofing work continues on the site foundation.
  • A crew will be making street repairs on Axel Drive and Milestone Street on Saturday, October 28th.

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • Site excavation has been paused while additional soil disposal logistics are coordinated.
  • Excavation on site will resume November 8th.
  • There will be no work this Saturday, October 28th.

Building Mock-Ups

  • The site fence and scrim for the Residential/Hotel mockups has been installed.
  • Construction on the mockups will begin Monday, October 30th.