As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation and concrete operations on site will continue.
- Rebar work within the site foundation is ongoing.
- Work will take place on Saturday, October 28th.
- Crews will start at 7:00am doing excavation work.
- All work will take place within the site.
- Soil will be transported via intermodal trucks via the site haul road to Beacon Park Yard.
- The first of two tower cranes has been erected and is operational. It is designed to move or “weathervane” in the wind.
Laboratory and Office Buildings
- Bulk excavation and concrete operations on site will continue.
- Rebar work is ongoing in preparation for the mat slab placement.
- Waterproofing work continues on the site foundation.
- A crew will be making street repairs on Axel Drive and Milestone Street on Saturday, October 28th.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- Site excavation has been paused while additional soil disposal logistics are coordinated.
- Excavation on site will resume November 8th.
- There will be no work this Saturday, October 28th.
Building Mock-Ups
- The site fence and scrim for the Residential/Hotel mockups has been installed.
- Construction on the mockups will begin Monday, October 30th.