As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation and concrete operations on site will continue.
- The first of two tower cranes will be erected October 13th-15th.
- This three-day operation will take place entirely within the site.
- An assist crane will be assembled on Friday and disassembled on Sunday.
- Work hours plan to be extended:
- Friday: Afternoon-8:00pm
- Saturday: 5:00am-6:00pm
- Sunday: 7:00am- until completion
- The crane components will arrive on numerous trucks.
Laboratory and Office Buildings
- Bulk excavation and concrete operations on site will continue.
- Ongoing rebar work in preparation for the mat slab placement.
- Waterproofing work continues on the site foundation.
- A large crane will be set up on October 21st.
- This crane will remain onsite through February and will support the mat slab placements.
- Due to the size of the crane a 12-hour workday is needed.
- Crews plan to begin at 6:00am and work until 6:00pm.
- There will be work on site Saturday, October 14th.
- Work will begin at 9:00am.
- Crews will be decommissioning temporary vibration monitoring on the roadway and working inside the site foundation.
Greenway
- This section of the site is currently being used for laydown space.
Treehouse Conference Center
- Site excavation has begun.
- Soil will be transported via intermodal trucks via the site haul road to Beacon Park Yard.
- A private haul road is being used to
- There will be work on site Saturday, October 14th.
- Crews will be excavating and hauling soil within the site to Beacon Park Yard.
- Work will begin at 9:00am.
Building Mock-Ups
- Punch list work on the two laboratory mockups will continue.