Enterprise Research Campus Update #11 (Week of October 16, 2023)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Bulk excavation and concrete operations on site will continue.
  • The first of two tower cranes will be erected October 13th-15th.
    • This three-day operation will take place entirely within the site.
    • An assist crane will be assembled on Friday and disassembled on Sunday.
    • Work hours plan to be extended:
      • Friday: Afternoon-8:00pm
      • Saturday: 5:00am-6:00pm
      • Sunday: 7:00am- until completion
    • The crane components will arrive on numerous trucks.

Laboratory and Office Buildings

  • Bulk excavation and concrete operations on site will continue.
  • Ongoing rebar work in preparation for the mat slab placement.
  • Waterproofing work continues on the site foundation.
  • A large crane will be set up on October 21st.
    • This crane will remain onsite through February and will support the mat slab placements.
    • Due to the size of the crane a 12-hour workday is needed.
      • Crews plan to begin at 6:00am and work until 6:00pm.
  • There will be work on site Saturday, October 14th.
    • Work will begin at 9:00am.
    • Crews will be decommissioning temporary vibration monitoring on the roadway and working inside the site foundation.

Greenway

  • This section of the site is currently being used for laydown space.

Treehouse Conference Center

  • Site excavation has begun.
    • Soil will be transported via intermodal trucks via the site haul road to Beacon Park Yard.
    • A private haul road is being used to
  • There will be work on site Saturday, October 14th.
    • Crews will be excavating and hauling soil within the site to Beacon Park Yard.
    • Work will begin at 9:00am.

Building Mock-Ups

  • Punch list work on the two laboratory mockups will continue.