Enterprise Research Campus Update #10 (Week of October 9, 2023)

Please note, no work will occur on Monday, October 9th in observance of the holiday. As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Bulk excavation and concrete operations on site will continue.
    • Soil is being hauled out via the site haul road to rail at Beacon Park Yard and being trucked out simultaneously.
  • The first of two tower cranes is targeted to be erected October 13th-15th.
    • This three-day operation will take place entirely within the site.
    • Work hours plan to be extended:
      • Friday: Afternoon into the night
      • Saturday: 5:00am-7:00pm
      • Sunday: 7:00am- until completion
    • The crane components will arrive on numerous trucks.
      • Some pieces will be required to be delivered on off hours due to their size.
  • Excavation crews will be working this Saturday, October 7th starting at 9:00am.

Laboratory and Office Buildings

  • Bulk excavation of the site continues.
  • Crews continue to line the site foundation with stone and place concrete mud mat.
  • Rebar work will begin in preparation for the mat slab placement.
  • Waterproofing work will begin on the foundation.

Greenway

  • This section of the site is currently being used for laydown space until crews mobilize in the coming months.

Treehouse Conference Center

  • Crews are planning to start preclearing and soil remediation operations.
    • Soil will be hauled out via rail at Beacon Park Yard and trucking simultaneously.

Building Mock-Ups

  • Punch list work on the two laboratory mockups will continue.