Enterprise Research Campus Update #8 (Week of September 25, 2023)

As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

Residential/Hotel

  • Bulk excavation of the site continues.
  • Soil will be hauled to Beacon Park Yard.
    • Trucks will use a private haul road to transport the soil to be taken off site via rail.
    • Soil will continue to be trucked out simultaneously.
  • Concrete operations will continue.
  • Crews are working to excavate a pad where the first of two tower cranes will be erected in October.
  • Crews will be working Saturday, September 23rd, within the excavation area.

Laboratory and Office Buildings

  • Bulk excavation of the site continues.
  • Crews will begin lining the site foundation with stone in preparation for mat slab placement.
    • This work will start Saturday, September 23rd.

Greenway

  • This section of the site is currently being used for laydown space until crews mobilize in the coming months.

Treehouse Conference Center

  • Crews will mobilize excavation operations on Tuesday, September 26th.
  • Bulk excavation of the site will start on Wednesday, September 27th.
    • Soil will be hauled out via rail at Beacon Park Yard.

Building Mock-Ups

  • Crews continue to work on the first two of five visual mockups.