As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
Residential/Hotel
- Bulk excavation of the site continues.
- Soil will be hauled to Beacon Park Yard.
- Trucks will use a private haul road to transport the soil to be taken off site via rail.
- Soil will continue to be trucked out simultaneously.
- Concrete operations will continue.
- Crews are working to excavate a pad where the first of two tower cranes will be erected in October.
- Crews will be working Saturday, September 23rd, within the excavation area.
Laboratory and Office Buildings
- Bulk excavation of the site continues.
- Crews will begin lining the site foundation with stone in preparation for mat slab placement.
- This work will start Saturday, September 23rd.
Greenway
- This section of the site is currently being used for laydown space until crews mobilize in the coming months.
Treehouse Conference Center
- Crews will mobilize excavation operations on Tuesday, September 26th.
- Bulk excavation of the site will start on Wednesday, September 27th.
- Soil will be hauled out via rail at Beacon Park Yard.
Building Mock-Ups
- Crews continue to work on the first two of five visual mockups.