As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference. Crews will not be working Labor Day weekend.
Residential/Hotel
- Bulk excavation of the site continues.
- Concrete operations will mobilize Tuesday.
- These operations will increase slowly as more of the site is excavated.
- Crews are working to excavate and place a concrete pad where the first of two tower cranes will be erected in October.
Laboratory and Office Buildings
- Bulk excavation of the site continues.
- Cross bracing installation will continue through the week.
Greenway
- This section of the site is currently being used for laydown space until crews mobilize in the coming months.
Treehouse Conference Center
- This section of the site is currently being used for laydown space until crews mobilize in the coming months.
Building Mock-Ups
- Work continues on two of the five mocks ups which assist in evaluating the building’s design and constructability.
- A pedestrian signage plan has been created for movement around the mockups.